Resource Cost Tables in MSP 2010


Microsoft Project 2010 provides you the option to change the Resource Standard Cost as well as Overtime cost by manually specifying the date. MSP 2010 automatically calculate the new Resource cost effective from the date you specify in your project budget automatically.

Select Resource then click on Resource Information.

















Select Cost tab from the Resource Information Dialog Box


























Now you can select the effective date from which your New Standard as well as Overtime rate are applicable for your project.
Microsoft Project 2010 provides 5 tables  namely A,B,C,D,E to store your different rates


























To change the default table used by your resource in Microsoft Project 2010, double click on your resource under Task Usage.Assignment Information dialog box will open, from there you can select the cost rate table you want to used in your project for your particular assignment.